Construction Planning and Management Sheet 1
-
1) Question.
The construction of ....... belongs to industrial construction.
Answer. -
2) Question.
The construction of residential building are treated as
Answer. -
3) Question.
When the construction cost of a work is between rupees twenty thousand and one lac, then it is said to be a major work.
Answer. -
4) Question.
The construction works costing above rupees one lac are classified as
Answer. -
5) Question.
The construction works costing below rupees twenty thousand are classified as
Answer. -
6) Question.
The proper planning, design and execution of the work is called modular co-ordination.
Answer. -
7) Question.
A golden rule for the procurement of construction stores is that
Answer.The golden rule of procurement in construction management ensures smooth progress of work without delay due to material shortage.
According to this rule:
2/3 (two-thirds) of the total required construction materials should be available at the site, and
1/3 (one-third) should be under procurement or in transit.
This maintains a continuous supply chain and prevents both work stoppage and overstocking. -
8) Question.
In construction work, the controlling function aims at
Answer. -
9) Question.
Each work should be planned with respect to
Answer. -
10) Question.
The main function of the construction management is
Answer.