Estimate and Costing Sheet 1
-
1) Question.
Pick up the correct statement from the following:
Answer. -
2) Question.
The floor area includes the area of the balcony up to
Answer.The floor area of a building is the usable covered area measured from the inner faces of the walls.
For estimation and valuation purposes:
- Rooms, kitchens, bathrooms, stores, etc. are taken as 100% of their area.
- Balcony area is generally included up to 50% of its actual area in the floor area calculation.
- Open terraces are usually not included in the floor area.
-
3) Question.
Carpet area does not include the area of
Answer.Carpet Area is the net usable area of a building that can actually be covered by a carpet. In many estimation and valuation objective questions, it excludes:
- Verandah, corridor and passage
- Bathroom and lavatory
- Kitchen and pantry
Therefore, all the areas mentioned in the options are excluded from the carpet area.
✅ Answer: 4. All the above
Quick Note
- Carpet Area = Actual usable living area.
- Floor Area = Carpet Area + area of kitchen, bathroom, pantry, etc.
- Plinth Area = Covered built-up area measured at floor level, including wall thickness.
-
4) Question.
The plinth area of a building not includes
Answer.Plinth Area is the built-up covered area measured at the floor level, including wall thickness.
It includes:
- Area of stair cover
- Lift well and lift landing
- Internal shafts for sanitary installations (up to about 2 m²)
- Walls and covered projections
It does not include:
- Cantilevered porch
- Cantilevered balcony
- Open terraces
- Architectural projections without floor support
Therefore,
✅ Answer: 4. Area of cantilevered porch
-
5) Question.
Pick up the incorrect statement from the following:
Answer. -
6) Question.
For the consturction of buildings, the subheads of the estimate are
Answer. -
7) Question.
Pick up the correct statement from the following:
Answer. -
8) Question.
The main factor to be considered while preparing a detailed estimate, is
Answer. -
9) Question.
Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
Answer.A Revised Estimate is prepared when the expenditure of a work is likely to exceed the amount of the original sanctioned estimate by more than 5%, due to:
- Increase in rates of materials or labour
- Change in quantities
- Alteration in design or specifications
Therefore, if the cost exceeds the sanctioned estimate by 5% or more, a revised estimate is required.
✅ Answer: 4. 5.0%
Exam Tip
- Revised Estimate → Excess over sanctioned estimate > 5%
- Supplementary Estimate → For additional items not included in the original estimate.
-
10) Question.
The most reliable estimate is
Answer.A Detailed Estimate is the most reliable estimate because:
- It is prepared from complete drawings and specifications.
- Quantities of all items are worked out in detail.
- Rates are applied item-wise.
- It gives the most accurate cost of the project.
Other estimates are approximate:
- Preliminary Estimate → Rough estimate for administrative approval.
- Plinth Area Estimate → Based on plinth area rate.
- Cube Rate Estimate → Based on volume of the building.
Reliability Order
- Detailed Estimate ✅ (Most accurate)
- Cube Rate Estimate
- Plinth Area Estimate
- Preliminary Estimate
Answer: Option 1 – Detailed Estimate ✅