Highway Sheet 17
-
1) Question.
The minimum value of camber provided for thin bituminous surface hill roads, is
Answer. -
2) Question.
The usual width of side drains along Highways in hilly region, is
Answer. -
3) Question.
The usual width of parpet walls along Highways in hilly region, is
Answer. -
4) Question.
According to IRC:52-1973, for a single lane National Highway in hilly region,
Answer. -
5) Question.
The wideth of the right of way, is influenced by
Answer. -
6) Question.
An upgrade is followed by a downgrade . The equation of the parabolic curve of lenght L to be introduced, is given by
Answer. -
7) Question.
The maximum distance of the apex of a vertical curve of length L from the point of intersection of two grades is
Answer. -
8) Question.
In an ideal transition curve, the radius of curvature
Answer. -
9) Question.
An ideal vertical curve is
Answer. -
10) Question.
The radius of curvature provided along a transtion curve, is
Answer. -
11) Question.
In the Group Index method of flexible pavement design, which one of the following factors decides the thickness of base and surface course ?
Answer. -
12) Question.
While designing the superelevation of a highway, its maximum value is fixed considering the need to -
Answer. -
13) Question.
While aligning a hill road with a ruling gradient of 1 in 20, a horizontal curve of radius 80 m is encountered. The compensated gradient on the curve will be -
Answer. -
14) Question.
Which one of the following is associated with "Limiting Gradient" on highways ?
Answer. -
15) Question.
In which one of the following types of bituminous constructions is proportioning of materials determined from laboratory tests ?
Answer. -
16) Question.
For sandy soils the most common method of stabilization is -
Answer.Sandy soils are generally stabilized with cement.The amount of cement required to stabilize depends upon the quantity and quality of fines contained in sandy soils and final compacted density.The cement required for sandy soils range between 5 and 12% by weight.Stabilization of soil with cements consists of adding cement to pulverized soil and permitting the mixture to harden by hydration of cement.The quantity of cement required for stabilization increases as soil plasticity increases.Note:Soil-lime stabilization: It is the process of adding lime to the soil to improve its properties like density, bearing capacity etc. The principle involved in lime-soil stabilization is the exchange of ions between lime and soil when added.When clayey soil is treated with lime, cation exchange takes place between them which increases plastic limit and reduces plasticity index which finally results in increase in stability of soil. This method is used mostly for clayey flocculated soil.Soil-bitumen stabilization: It is applied to highways and airfield construction. It is the method of designing and mixing local soil or aggregates with bituminous materials to form a stable and waterproof base course.Bitumen stabilization is used for:-a) For binding soil particles together for purpose of supplying cohesion for non-mechanical stabilized granular material. -
17) Question.
Select the incorrect statement ?
Answer. -
18) Question.
In hill roadds the side drains are provided -
Answer. -
19) Question.
The walls which are necessary on the hill side of roadway where earth has to be retained from slipping is known as -
Answer. -
20) Question.
In highway construction on superelevated curves, the rolling shall proceed from
Answer.